Login
download old movies
Sprint 6 Progress: 07-Apr-2006
Mon
10
Apr '06

The latest burn down graph for sprint 6 is available here. This sprint is now code complete, with just the test phase to do. There’s now two sprints awaiting testing due to holidays and other things we’ve not progressed those yet, but this week we’ll have to get to it.

As you can see this sprint has finished early as the tasks were not as complex as I thought they would be when I estimated it. This is good, as it’ll help us make up time lost in sprint 5. :)

Tags: , ,

One Response to “Sprint 6 Progress: 07-Apr-2006”
garyshort.org » Blog Archive » The Holidays are Over Says:

[...] Well the holidays are over and I’m back to work today. Still not to worry. I’ve updated the progress on sprint 6 for the netBake product. You can find you can keep up with the latest across on the product blog here. [...]

Leave A Reply