| Sprint 6 Progress: 07-Apr-2006 | |||||||||||||||||
The latest burn down graph for sprint 6 is available here. This sprint is now code complete, with just the test phase to do. There’s now two sprints awaiting testing due to holidays and other things we’ve not progressed those yet, but this week we’ll have to get to it. As you can see this sprint has finished early as the tasks were not as complex as I thought they would be when I estimated it. This is good, as it’ll help us make up time lost in sprint 5. Tags: Scrum, bakery software, netBake |
|||||||||||||||||